Alaska Supreme Court Opinions made Available byTouch N' Go Systems and Bright Solutions


Touch N' Go
®, the DeskTop In-and-Out Board makes your office run smoother.

 

You can search the entire site. or go to the recent opinions, or the chronological or subject indices. Johnson Construction Company v. Albin Carlson & Co., Contractors (6/13/2025) sp-7773

Johnson Construction Company v. Albin Carlson & Co., Contractors (6/13/2025) sp-7773

        Notice:  This opinion is subject to correction before publication in the PACIFIC REPORTER.   

        Readers are requested to bring errors to the attention of the Clerk of the Appellate Courts,  

        303 K Street, Anchorage, Alaska 99501, phone (907) 264-0608, fax (907) 264-0878, email  

        corrections@akcourts.gov.  

  

  

                   THE SUPREME COURT OF THE STATE OF ALASKA  

  



MORRIS O. JOHNSON JR. d/b/a                                )      

JOHNSON CONSTRUCTION                                       )         Supreme Court Nos. S-18615/18625  

COMPANY,                                                   )      

                                                           )         Superior Court No. 3AN-16-07503 CI  

                             Appellant and                 )      

                             Cross-Appellee,               )         O P I N I O N  

                                                           )      

          v.                                               )        No. 7773 - June  13, 2025  

                                                           )                                   

ALBIN CARLSON & CO., and                                   )  

PATRICK ALBIN CARLSON JOINT    )  

VENTURE, LLC,                                              )  

                                                           )  

                             Appellees and                 )  

                             Cross-Appellants.             )  

                                                           )  

                   

                  Appeal from the Superior Court of the State of Alaska, Third  

                  Judicial District, Anchorage, William F. Morse, Judge.  

  

                  Appearances:    Kevin  T.  Fitzgerald,  Ingaldson  Fitzgerald,  

                  P.C., Anchorage, for Appellant and Cross-Appellee.   Sarah  

                  C. Gillstrom, Davis Wright Tremaine LLP, Anchorage, for  

                  Appellees and Cross-Appellants.  

  

                  Before:    Maassen,  Chief  Justice,  and  Carney,  Borghesan,  

                  Henderson, and Pate, Justices.  

                   

                  CARNEY, Justice.  

                   

                   

                   

  


----------------------- Page 2-----------------------

       INTRODUCTION  



               A contractor hired a subcontractor to undertake part of the construction of  



a remote bridge.  The initial scope of the contracted work soon changed.  Neither the  



contractor  nor  the  subcontractor  kept  detailed  records  of  the  changes  and  their  



associated costs.  Years after the project was completed, the subcontractor sued for  



damages, claiming that it had not been paid for the work it completed.  



               The superior court concluded that the subcontract did not govern the extra  



work.  It awarded the subcontractor damages on some claims and denied others.  The  



court also precluded the subcontractor from pursuing some claims at trial because of  



discovery  violations.    The  court  found  that  the  contractor  was  the  prevailing  party  



following trial and awarded attorney's fees to the contractor.   



               Both the contractor and subcontractor appeal.  We conclude that it was an  



abuse of discretion to preclude  the subcontractor from pursuing claims without  first  



considering less severe sanctions.  We also reverse some of the damages awards and  



vacate the court's prevailing party determination and resulting  attorney's fees  award.   



We otherwise affirm the judgment and remand for further proceedings consistent with  



this opinion.    



       FACTS AND PROCEEDINGS  



       A.      Facts  



               Because the legal issues in this appeal are based upon specific events that  



occurred during the years that the bridge was being constructed, we set forth the facts  



in some detail.  



               In  2010,  a  Chicago-area  construction  company,  Patrick  Albin  Carlson  



Joint Venture, LLC (PAC) was awarded a $1.7 million contract from the United States  



Forest Service to design and build a trail bridge over  a river in the Chugach National  



Forest.  The bridge's location was ten miles from the nearest road but was accessible  



by railroad for part of the year.  When the railroad was not in operation, however, crews  



could only access the site by boat, snowmachine, or helicopter.   



                                               -2-                                          7773  


----------------------- Page 3-----------------------

               PAC   is   comprised   of   Albin   Carlson   &   Co.   (Albin)   and   Patrick  



Engineering   Inc.     It   subcontracted   with   one   company   to   build   the   bridge;   it  



subcontracted with another, Goode Construction, to complete earthwork and assemble  



and lift the bridge into place.   



               PAC also entered a subcontract with Johnson Construction Co. (Johnson)  



to  drive  the  piles  to  support  the bridge.    Johnson  is  a  sole proprietorship of Morris  



Johnson,  a contractor and crane operator.  Johnson initially submitted a $950,000 bid  



to perform nearly all of the work for PAC, but PAC subcontracted with Johnson only  



to drive temporary and permanent piles for the bridge.   



               1.      The subcontract   



               The  subcontract  between  PAC  and  Johnson  incorporated  by  reference  



work identified in  two  separate work orders.  Work Order No. 1 directed Johnson to  



install eight permanent piles, four on each side of the river.  Work Order No. 2 required  



Johnson to install two temporary piles on each side of the river to support the bridge as  



it was being erected.   The  orders required  the work  to be substantially completed by  



October  1,  2011.    PAC  agreed  to  pay  Johnson  $82,500  for  Work  Order  No.  1  and  



$30,000 for Work Order No. 2, for a total of $112,500.   



               The  subcontract  contained  a  changes  clause  allowing  PAC  to  alter  the  



scope of the work.  The clause required that such changes "shall be authorized only by  



a written and properly executed Change Order from [PAC], or by a verbal or written  



directive from [PAC's] Project superintendent based upon directions from the [Forest  



Service]."  Verbal or written changes ordered by the superintendent were required to be  



documented in a change order by PAC as promptly as possible.  Finally, the subcontract  



provided that "[n]o change in the Work, whether by way of alteration or addition to the  



Work, shall be the basis of an addition to the amount to be paid to [Johnson] . . . unless  



and until such alteration or addition has been authorized by a Change Order executed  



by [PAC]."   



                                                -3-                                            7773  


----------------------- Page 4-----------------------

                 The subcontract also contained various recordkeeping and documentation  



requirements.  As a "condition precedent" to payment, it required Johnson to give PAC  



an invoice with receipts, original waivers of lien, and other evidence showing Johnson's  



expenses related to the work.  It also provided that:  



                         Whenever the requirements of the  [contract between  

                 PAC and the Forest Service]  are such that as a prerequisite  

                 to  receipt  of  payment,  [PAC]  must  furnish  the  [Forest  

                 Service] with documentation of any nature whatsoever from  

                 [Johnson] . . . , including but not limited to certified payrolls,  

                 compliance statements and other documents required under  

                 applicable laws or  [that contract], [Johnson] shall promptly  

                 furnish [PAC] with such required documentation, and [PAC]  

                 may withhold payment until such documentation has been  

                 furnished.   

                         . . . .  



                         Final  payment  shall  in  no  event  become  due  to  

                 [Johnson] until  . . . [Johnson] submits to [PAC], as may be  

                required by [PAC]:  (i) an affidavit that all payrolls, bills for  

                 materials  and  equipment,  and  all  other  indebtedness  of  

                 [Johnson] related to its performance of the Work, have been  

                 fully paid or otherwise satisfied, and (ii) complete and final  

                 lien waivers from [Johnson] . . . .   



                 2.      The 2011 construction season  



                 The project quickly encountered delays.  Johnson mobilized equipment to  



the construction site in late September 2011 and began driving the permanent piles on  



the east side of the river.  Soon after beginning, Johnson hit an underground obstruction  



that drove one or more piles out of alignment.  David Voss, PAC's onsite representative,  



directed Johnson to pause its work on the east side and begin driving the west side piles.   



                 Again Johnson encountered trouble.  Although it had been able to move  



equipment to the east side of the river by rail, Johnson  could not do the same  on the  



west side because the bank was too steep.  Nor could its equipment ford the river.  The  



parties  decided  that  Johnson  would  build  an  ice  bridge  over  the  river  to  move  its  



equipment to the west side.  PAC agreed to compensate Johnson for this work on a time  



                                                    -4-                                                7773  


----------------------- Page 5-----------------------

and materials basis.  Johnson built the ice bridge as soon as temperatures and snowfall  



allowed its employees to snowmachine to the site.   



                 PAC requested Johnson's certified payrolls,  as  required by  its  contract  



                                                                            1 

with the Forest Service, several times throughout the project.   In mid-November 2011  



Voss sent Morris Johnson the certified payroll form and explained that it "need[ed] to  



be filled out."  Two weeks later, PAC again sought the certified payrolls from Morris  



Johnson and sent him the form to be completed.    Johnson  did not  send  any certified  



payrolls to PAC in 2011.  But PAC paid Johnson's first invoice - $36,250 for driving  



the permanent piles under Work Order No. 1 and $15,000 for supplying and installing  



temporary piles under Work Order No. 2.   



                 3.      The 2012 construction season  



                 Johnson  completed  the  ice  bridge  in  March  2012.    It  then  moved  its  



equipment to the west side of the river, where it  remained until work resumed in the  



spring.   



                 That  spring  Voss  approved  Johnson's  request  to  purchase  a  boat  to  



facilitate site access and orally agreed that PAC would reimburse Johnson for its use of  



the boat.  He also directed Johnson to take over some of the bridge lifting work that had  



been assigned to Goode Construction.  The added work required Johnson to bring crane  



mats and an additional, much larger crane to the work site.   



                 In  June  PAC  again  requested  Johnson's  certified  payrolls.    Johnson  



eventually provided its certified payrolls covering October 9, 2011 to August 4, 2012.   



                 In  July  PAC  replaced  Voss  with  Neil  Hunt.    In  September  PAC  and  



Johnson prepared Invoice 2, billing PAC $50,000 under Work Order Nos.  1 and 2 for  



driving the permanent piles, welding pile caps on the west side piles, and installing  



some temporary piles.  PAC paid the invoice.   



                                                                                                              

        1        See 29 C.F.R. § 5.5(a)(3) (2009).  



                                                    -5-                                                 7773  


----------------------- Page 6-----------------------

                Also in September, Hunt sent Morris Johnson an email summarizing the  



agreed-upon  extra  work.    Among  the  work  included  was  Johnson's  previous  work  



building the ice bridge.  The email reiterated that the work would be compensated on a  



time and materials basis.   



                Hunt also identified additional work to be completed:    additional crane  



work, support  for  Goode Construction  on  the bridge superstructure, and dirt work to  



build pads to stage and lift the bridge.  The email stated that this work was also to be  



done on a time and materials basis and would include equipment rates provided by  



Johnson.  It also stated that Johnson would provide travel to and from the worksite via  



boat.    Hunt  concluded  the  email  by  requesting  to  discuss  the  additional  work  with  



Morris Johnson so that PAC could issue a change order.    There is no evidence of a  



response from Johnson.   



                In October Hunt sent Morris Johnson a proposed written change order  



authorizing Johnson to lift the bridge into place.  Under the proposed terms, Johnson  



would be paid $33,000 to mobilize and demobilize a crane to the worksite to lift and  



install the bridge.  Hunt proposed authorizing up to $20,000 in labor costs at a rate of  



$130 per hour.  Neither PAC nor Johnson signed the change order.   



                Johnson completed the work  specified in the unsigned change order.   It  



also built a temporary dirt abutment on the west side of the river to complete the lifting  



work it had assumed from Goode Construction.  The bridge was fully assembled by late  



fall  or  early  winter  2012  but,  due  to  weather,  it  was  not  installed  until  June  2013.   



Johnson's equipment was left at the worksite over the winter.   



                Johnson submitted two invoices to PAC in October, both dated October  



2, 2012.  The first billed PAC $12,500 for the remaining work under Work Order Nos.  



1 and 2.  The second invoice was for  $16,500 for crane mobilization to the worksite.   



PAC paid both invoices.   



                                                 -6-                                             7773  


----------------------- Page 7-----------------------

                PAC prepared another invoice in October 2012, billing itself $20,000 for  



Johnson's bridge installation labor.  It paid the invoice.  Morris Johnson did not agree  



to the invoice, object to the payment, or ask what it was for.   



                In late December 2012, Hunt asked Morris Johnson for certified payrolls  



from August 2012 to December 2012.  There is no record of a response.   



                4.      The 2013 construction season and project closeout   



                Hunt  requested  certified  payrolls  again  in  January  2013.    In  late  April  



Morris Johnson responded that he would try to send them to Hunt that week.   



                Johnson finished the bridge installation in June.  PAC notified the Forest  



Service  that  the  bridge  was  complete  and  awaiting  inspection.    PAC  and  all  of  its  



subcontractors removed their equipment from the worksite by late July.   



                As part of its project closeout in August and September 2013, PAC  sent  



Morris Johnson three requests for Johnson's final invoice, final payment information,  



and certified payrolls.  Morris Johnson did not respond to these requests.   



                In December 2013 PAC prepared a draft final invoice for Johnson.  The  



invoice included $40,000 for labor costs; $16,500 for crane demobilization; $35,000 for  



                                                                 2                                      3 

the 2011-2012 winter work; $3,000 for pile changes;  and $5,000 for the boat rental.    



PAC  did not send  the draft invoice to Johnson or pay  the amount that it estimated it  



owed Johnson.   



                There was no further communication between PAC and Johnson until July  



2016.  At that time Morris Johnson contacted PAC seeking final payment for the extra  



work.    He  forwarded  Hunt's  September  2011  email  describing  the  extra  work  that  



Johnson had completed or was to perform.   PAC and Johnson exchanged emails for  



                                                                                                           

        2       The superior court mistakenly recorded the cost of the pile changes as  

$5,000.   

        3       The invoice  also  gave  PAC  $5,000 credit for  a  truck that Johnson had  

purchased from PAC during the project.  PAC thus calculated that the total amount it  

owed Johnson was $94,500 (40,000 + 16,500 + 35,000 + 3,000 + 5,000 - 5,000).   



                                                   -7-                                               7773  


----------------------- Page 8-----------------------

several months, searching for documents.  On June 1, 2017, PAC sent the $94,500 draft  



invoice it prepared in 2013 but never shared.  On June 7 Morris Johnson responded with  



a demand for $1.4 million.  



        B.       Proceedings  



                 Johnson  filed  suit  against  PAC  and  Albin  in  July  2016,  seeking  over  



$600,000  in  damages  for  work  performed  under  the  subcontract  including  labor,  



transportation, and equipment costs.  Johnson served PAC and Albin with the complaint  



in August 2017.   



                 1.      Summary judgment motions  



                 PAC and Albin moved for summary judgment.    They first argued that  



Johnson was not entitled to damages because it did not comply with several conditions  



precedent requiring Johnson to submit certified payrolls and a final payment application  



before it was entitled to payment.  PAC and Albin also argued that Johnson's claim was  



a total cost claim and should be dismissed because Johnson could not meet the threshold  



                                     4 

test for asserting such a claim.   Under that test, a party may not assert a total cost claim  



unless it proves that  



                 (1) the nature of the particular losses make it impossible or  

                highly  impracticable  to  determine  them  with  a  reasonable  

                 degree of accuracy; (2) the plaintiff's bid or estimate was  

                realistic; (3) its actual costs were reasonable; and (4) it was  

                not responsible for the added expenses.[5]  



PAC and Albin claimed that Johnson's failure to maintain records for the costs of extra  



work disqualified it from proving the first element and therefore precluded it from using  



the total cost method.   



                                                                                                             

        4       See Geolar, Inc. v. Gilbert/Commonwealth Inc. of Mich.,  874 P.2d  937,  

944-45 (Alaska 1994).   

        5       Id. at 945 (quoting Mun. of Anchorage v. Frank Coluccio Constr. Co. , 826  

P.2d 316, 325 (Alaska 1992)).   



                                                    -8-                                                7773  


----------------------- Page 9-----------------------

                 Johnson opposed and filed a cross-motion for summary judgment.  It first  



argued  that  the  extra  work  was  governed  by  separate  oral  agreements,  not  the  



subcontract.  It also contended that even if the subcontract controlled, Johnson was still  



entitled  to  recovery  because  PAC  and  Albin  waived  the  recordkeeping  provisions.   



Johnson further argued that it was entitled to summary judgment on liability because  



PAC and Albin did not dispute that they agreed to pay Johnson for extra work on a time  



and materials basis and that Johnson performed the extra work.   



                 The  superior  court  denied  both  motions.    It  concluded  that  each  party  



                                                                                        6 

raised questions of fact, so neither was entitled to summary judgmen t.    



                 PAC and Albin moved  for reconsideration.   They  argued that Johnson's  



failure to present evidence satisfying the threshold requirements was fatal to its claims.   



The superior court agreed that Johnson had not met the test for a total cost claim but  



concluded  that  "[t]here  are  other  ways  to  prove  damages."    It  therefore  denied  



reconsideration.   



                 In January 2021 PAC and Albin served Johnson with an Alaska Civil Rule  



                                                                                      7 

68 offer of judgment for   $243,000,  including prejudgment interest.   Johnson did not  



accept the offer.   



                 2.      Motion in limine  



                 A month before trial was scheduled to begin  in  March 2021, PAC and  



Albin  filed  a  motion  in  limine  to  exclude  evidence  supporting  Johnson's  damages  



claims for its employees' labor, Morris Johnson's labor, equipment charges, materials,  



                                                                                                               

        6        Thomas  v.  Joseph  P.  Casteel  Tr. ,  496  P.3d  403,  409  (Alaska  2021)  

("[S]ummary judgment is appropriate only when no reasonable person could discern a  

genuine   factual   dispute   on   a   material   issue."   (alteration   in   original)   (quoting  

Christensen v. Alaska Sales & Serv., Inc., 335 P.3d 514, 520 (Alaska 2014))).   

        7        Under  Rule  68,  a  party  that  declines  a  valid  offer  of  judgment  from  

multiple defendants must pay a percentage of the offering parties' attorney's fees if the  

final judgment is at least 10% less favorable than the offer.   



                                                     -9-                                                 7773  


----------------------- Page 10-----------------------

and transportation.   They argued that  Johnson  violated  Civil Rule 26(a) by failing to  



provide documentation and computation for its claimed damages.  The court partially  



granted the motion.  Considering each damages claim in turn, the court concluded that  



Johnson  failed  to  provide  sufficient  documentation  to  support  its  claims  for  Morris  



Johnson's  labor,  snowmachine  and  boat  use,  travel  labor,  and  trucking  costs.    It  



therefore precluded Johnson from pursuing these damages claims at trial.   



                 The  court  also  recognized  that  a  total  cost  claim  was  "a  disfavored  



method" that may be used only in limited circumstances.  It prohibited Johnson from  



pursuing this method at trial but allowed Johnson to proceed using either the actual cost  



                             8 

or jury verdict method.    



                 Johnson moved for reconsideration.  The court denied reconsideration but  



nevertheless allowed Johnson to present evidence for the excluded claims.   The court  



concluded that because its legal rulings and factual findings would likely be appealed,  



it would be "more efficient" to hear the evidence and make contingent findings on the  



precluded claims.   



                 3.      Trial   



                 A ten-day bench trial was held in June and July 2021.    Johnson called  



Morris Johnson and an expert in equipment rental rates as witnesses.  Morris Johnson  



described the challenges involved in constructing the bridge and the ad hoc relationship  



he had with PAC and PAC's representatives.   



                                                                                                               

         8       The jury verdict method is a method of calculating damages when actual  

costs are not available.  Power Constructors, Inc. v. Taylor & Hintze , 960 P.2d 20, 41  

(Alaska 1998).  Under this approach, the contractor may "present evidence of the cost  

of additional work to the finder of fact[,] including any actual cost data, accounting  

records, estimates by law and expert witnesses, and calculations from similar projects."   

Id. (alteration in original) (quoting Frank Coluccio Constr. Co. , 826 P.2d at 325).  



           



                                                    -10-                                                 7773  


----------------------- Page 11-----------------------

               Johnson  claimed  it  was  owed  nearly  $4.5  million  for  the  extra  work,  



including $36,987 for the snowmachines; $67,848 for the boat; $356,750 for  Morris  



Johnson's labor; and about $2.9 million for equipment rentals.  Morris Johnson testified  



that  David  Voss,  PAC's  onsite  supervisor,  agreed  to  a  daily  rate  of  $250  per  



snowmachine and Johnson used 3 snowmachines for 36 days.  He also said that Voss  



agreed to pay $1,000 per day to use Johnson's boat  and that it was used for 61 days.   



Morris Johnson estimated that he worked 1,427 hours for design and engineering related  



to the extra work and that his time was worth $250 per hour because he had previously  



paid engineers and other professionals $250 per hour.   



               Morris  Johnson  testified  that  Voss  had  visited  his  equipment  yard,  



selected the equipment that he wanted, and was informed of their rental rates.  Johnson  



then  called  Kirk  Currey  as  an  expert  to  testify  about  rental  rates  and  terms  for  



construction equipment.   Currey gave market rates for the equipment Morris Johnson  



said PAC rented, and acknowledged that some were based on rates Morris Johnson told  



him.  He estimated that the reasonable rental value for the equipment was  about $2.9  



million.   



               PAC and Albin presented three witnesses.  Neil Hunt, the  senior project  



manager who oversaw the bridge construction from mid-2012 until 2014, described the  



extra  work  that  PAC  had  approved.    He  also  testified  about  his  efforts  to  obtain  



Johnson's  certified  payrolls  and  other  documents.    The  former  president  of  Patrick  



Engineering, Jeffrey Schuh, testified that he had never seen a subcontractor claim that  



extra work was not governed by the subcontract's terms.  He testified that PAC had not  



waived  any  of  the  subcontract  requirements  for  Johnson.    Paul  Keating,  Patrick  



Engineering's vice president of construction, testified about PAC's usual requirements  



before paying subcontractors.  He stated that before a subcontractor would be paid, the  



subcontractor was required to provide a final waiver of any lien and an accounting of  



actual costs, along with contemporaneous time and materials documentation signed by  



PAC's onsite supervisor.   



                                             -11-                                          7773  


----------------------- Page 12-----------------------

                After  eight  days  of trial, Albin moved  to dismiss the claims against it,  



arguing that Johnson's evidence and the relevant law established that Johnson was not  



                              9 

entitled to relief from it.   Albin argued that it was not a party to the contracts between  



Johnson and PAC and  that  Johnson had not presented any evidence that  Albin  was  



otherwise liable.  The court granted the motion on the record and dismissed Johnson's  



claims against Albin.   



                 4.      Findings of fact and conclusions of law  



                 The superior court issued its findings  of fact  and conclusions  of law  in  



March 2022.    It  determined  that, regardless of whether the subcontract governed the  



extra work, the parties agreed Johnson was to be compensated on a time and materials  



basis.   That agreement, the court concluded, required Johnson to document the extra  



work performed and materials used.    The court found that  Johnson largely failed to  



provide contemporaneous documentation  of the materials used and that  "[t]he parties  



engaged in skeletal, and at times inconsistent, communications that left the terms of the  



agreement uncertain."   It therefore concluded that PAC was required to pay  Johnson  



only for the costs of material and some services that Johnson could prove PAC agreed  



to pay and for which Johnson could reasonably show the costs incurred.  Where actual  



costs were not available, the court used the jury verdict method to determine Johnson's  



damages.   



                 The court found that PAC owed Johnson $191,443.42: $33,000 for the  



demobilization of two cranes; $11,280 for helicopter use; $17,605 for a man lift rental;  



$30,000 for boat use; $99,000 for overwintering equipment in 2011-12  and 2012-13;  

and $513.42 for pile tips for the permanent abutments.10   The court next turned to its  



                                                                                                             

        9       Under  Civil  Rule  41(b),  a  defendant  in  a  bench  trial  may  move  for  

dismissal "on the ground that upon the facts and the law the plaintiff has shown no right  

to relief" after the plaintiff's evidence has been presented.  

        10       There was a minor calculation error in the order.  Based on the court's  

findings, the total award should have been $191,398.42.  



                                                   -12-                                                7773  


----------------------- Page 13-----------------------

contingent findings for the precluded  claims.  Based on Johnson's 2012 labor records  



and Morris Johnson's testimony that the snowmachines he used would rent for $250  



per day, the court found that PAC would  have  owed  Johnson $15,000 for use of the  



snowmachines if the snowmachine claim had not been precluded.  The court also found  



that the contingent value of Morris Johnson's labor was $128,700.   



               PAC filed a motion for reconsideration, which the court granted in part.   



The  court  acknowledged  that  it  "sidestepped"  the  issue  of  whether  the  subcontract  



governed the extra work, and, at PAC's insistence,  "clarifie[d] what it left opaque,"  



finding that the extra work was not covered by the subcontract.  The court found that  



the "parties engaged in an ad hoc relationship that deviated from the strict requirements  



of the subcontract when it was convenient for them to do so."  It stated that it would not  



allow  PAC  "to  weaponize  apparent  tolerance"  for  Johnson's  noncompliance  by  



"transforming  a  longstanding  course  of  conduct  into  a  last-minute  trap  that  would  



enable it to avoid payment" for the extra work.   



               After reconsideration the court reduced the award for crane mobilization  



and demobilization from $33,000 to $8,250.  It explained that Johnson agreed that PAC  



had  already  paid for  the  first  crane's demobilization  and part of  the  second  crane's  



mobilization under Work Order No. 2 .  It also reduced the $30,000 award for the boat  



use, concluding that PAC should reimburse Johnson for the diminished value of the  



used boat instead of its full cost when new.  The court set that value at $10,000.  Based  



on  those  reductions,  the  court  reduced  Johnson's  total  award  from  $191,443.42  to  



$146,693.42.   



               The court also granted PAC's motion to be declared the prevailing party  



under Rule 68.  It determined that prejudgment interest began to accrue on June 7, 2017,  



the  day  Johnson  sent  its  first  specific  demand for payment.    It  therefore found  that  



Johnson failed to beat PAC's $243,000 offer of judgment, and concluded that PAC was  



entitled to attorney's fees of $90,993.79.  Albin separately moved for attorney's fees as  



provided by Rule 82; the court granted its request for $77,141.66.   



                                              -13-                                          7773  


----------------------- Page 14-----------------------

                 Johnson  appeals  the order precluding it from pursuing certain  damages  



claims,  several  damages  awards,  and  the  prevailing  party  determination  related  



attorney's fees.  PAC cross-appeals the denial of summary judgment, several damages  



awards, and Johnson's overall recovery.   



         STANDARD OF REVIEW  



                 We   review   the   superior   court's   discovery   decisions   for   abuse   of  

discretion.11    An  abuse  of  discretion  exists  when  the  court's  decision  is  manifestly  



unreasonable.12  We review questions of law, including the interpretation of court rules,  



de novo.13   In doing so,  "we adopt  the rule of law that is most persuasive in light of  



precedent, reason, and policy."14    



                 We  also review  contract interpretation  de novo.15   "Where the superior  



court  considers  extrinsic  evidence  in  interpreting  contract  terms,  however,  we  will  



review the superior court's factual determinations for clear error and inferences drawn  

from that extrinsic evidence for support by substantial evidence."16    



                 "We 'review denials of summary judgment motions de novo to determine  



. . . whether the moving party is entitled to judgment as a matter of law, viewing all  

facts in the light most favorable to the non-movant.' "17  



                                                                                                               

        11       Punches v. McCarrey Glen Apartments, LLC , 480 P.3d 612, 619 (Alaska  

2021).   

        12       Id.   



        13       See Shea v. State, Dep't of Admin., Div. of Ret. & Benefits, 204 P.3d 1023,  

1026 (Alaska 2009).    

        14       Id.    



        15       Nautilus Marine  Enters., Inc. v. Exxon Mobil Corp., 305 P.3d 309, 315  

(Alaska 2013).    

        16       Id. (quoting  Villars v. Villars, 277 P.3d 763, 768 (Alaska 2012)).   



        17       Baker  v.  Duffus ,  542  P.3d  1153,  1155  (Alaska  2024)  (alteration  in  

original) (quoting State, Dep't of Health & Soc. Servs., Div. of Fam. & Youth Servs. v.  

Sandsness, 72 P.3d 299, 301 (Alaska 2003)).  



                                                    -14-                                                 7773  


----------------------- Page 15-----------------------

                "A trial court's determination of damages is a finding of fact" which we  

review for clear error.18  We apply our independent judgment, however, when deciding  



whether a damages award was "based on an erroneous application of law."19  And while  



we review the  award of attorney's fees for  abuse of discretion,20  the issue of "when  



interest begins to accrue is a question of law, subject to [our] independent judgment."21  



        DISCUSSION  



                Johnson raises a number of arguments.  It challenges the court's decision  



to preclude it from pursuing  certain  damages claims, the amount of several  damages  



awards, and the prevailing party determination and attorney's fee award.    



                PAC  cross-appeals  raising  several  different  issues.    It  argues  that  the  



superior court erred by allowing any recovery because the subcontract governed the  



extra  work  and  Johnson  did  not  comply  with  certain  conditions  precedent  in  the  



subcontract.  PAC also challenges the superior court's denial of summary judgment on  



the total cost claim, its use of the jury verdict method to measure damages, and several  



damages awards.   



                We largely affirm the superior court's decisions.   But because it was an  



abuse of discretion to prohibit Johnson from pursuing the claims for snowmachine use  



and Morris Johnson's labor without  first considering lesser sanctions, we reverse the  



order precluding  claims for  those damages.  We also reverse the awards for Morris  



Johnson's labor and boat use and remand for the superior court's reconsideration.  As a  



result,  we vacate  and remand the prevailing party determination and attorney's fees  



award.    



                                                                                                           

        18      Galipeau v. Bixby, 476 P.3d 1129, 1134 (Alaska 2020) (quoting Haines v.  

Comfort Keepers, Inc., 393 P.3d 422, 427 (Alaska 2017)).  

        19      Id. (quoting Haines, 393 P.3d at 427).  



        20      Lee v. Konrad , 337 P.3d 510, 518 (Alaska 2014).    



        21      Hofmann v. von Wirth , 907 P.2d 454, 455 (Alaska 1995).  



                                                  -15-                                               7773  


----------------------- Page 16-----------------------

        A.       Johnson's Precluded Damages Claims  



                 The  superior  court  partially  granted  PAC's  pretrial  motion  to  preclude  



Johnson from pursuing  certain claims due to discovery violations.   It  concluded  that  



Johnson violated Civil Rule 26 because it had not provided sufficient documentation in  



pretrial discovery for several damages claims, including snowmachine use and Morris  



Johnson's labor.    The court  then  prohibited Johnson from pursuing these claims  for  



damages,  although  it  permitted  the  subcontractor  to  present  evidence  to  support  its  



contingent findings on them.  Johnson appeals, arguing that it complied with Rule 26's  



requirements.   



                 Rule 26(a) requires parties to make initial disclosures of "all categories of  



damages claimed" and "the documents or other evidentiary material . . . on which such  

claims are based."22   The rule does  not  specify a required level of documentation; it  



simply obliges a party to disclose the documents, if any, on which a damages claim is  



based.  If a party has not relied on documents to support its claims, the party need not  

disclose any.23  We recently stated that "[p]laintiffs in a contract suit are not required to  



present documentary evidence to substantiate their damages."24  It therefore was legal  



error to prevent Johnson from pursuing  claims  for the snowmachine use and Morris  



Johnson's labor because of Johnson's skeletal discovery documentation.   



                 PAC  argues  that  we  should  affirm  the  superior  court's  preclusion  of  



Johnson's  claims  because  Johnson  also  failed  to  provide  "a  computation  of  each  



category of special damages" as required by Rule 26(a)(1)(G).  According to PAC,  a  



"computation" is something more than a "lump sum" and "contemplates some analysis"  



showing  how  Johnson  calculated  the  claimed  amount.    Johnson,  on  the  other hand,  



                                                                                                              

        22       Alaska R. Civ. P. 26(a)(1)(G).  



        23       See  Griffith v. Hemphill, 521 P.3d 584, 590-91 (Alaska 2022) (affirming  

damages award based solely on plaintiff's testimony).   

        24       Id. at 590.  



                                                    -16-                                                7773  


----------------------- Page 17-----------------------

contends  that  it  satisfied  the  rule  and  addressed  PAC's  computation  concerns  in  its  



supplemental disclosures.   



                 Even assuming that Johnson violated its discovery obligation under Rule  



26(a)(1)(G) by failing to disclose the computation of its damages,  it was an abuse of  



discretion  to  impose  claim-ending  sanctions  without  first  considering  less  severe  



sanctions.  The court has discretion to impose sanctions on a party that fails to make the  

required  pretrial  disclosures  "without  substantial  justification."25    In  most  cases,  



excluding the undisclosed evidence appropriately remedies the violation.26  But in some  



circumstances, the court may impose more severe sanctions, like dismissing a part of  

the action or refusing to allow the offending party to support designated claims.27  



                 We   have   cautioned   that   claim-   or   litigation-ending   sanctions   are  

appropriate only in "extreme cases."28  Before imposing such sanctions, the court must  



consider whether less severe alternatives would adequately protect the opposing party  

and deter other discovery violations.29  And the  court may not issue an order that has  



the effect of dismissing a claim unless it finds that the party acted willfully .30  We have  



specifically  held  that  preclusion  for  failing  to  make  pretrial  disclosures  "should  be  

imposed only as a last resort if a continuance or other sanction is inadequate."31   



                 There  is  no  indication  in  the  record  that  the  superior  court  considered  



whether a lesser sanction would adequately remedy any prejudice caused by Johnson's  



                                                                                                               

        25       Alaska R. Civ. P. 37(c)(1).  



        26       See id. (making exclusion default remedy).  



        27       See id.   



        28       Khalsa v. Chose , 261 P.3d 367, 372 (Alaska 2011) (quoting DeNardo v.  

ABC Inc. RVs Motorhomes, 51 P.3d 919, 922 (Alaska 2002)).  

        29       Id. at 372-73; accord Alaska R. Civ. P. 37(b)(3)(D).   



        30       Alaska R. Civ. P. 37(b)(3).  



        31       Urban v. Urban, 314 P.3d 513, 517 (Alaska 2013).  



                                                    -17-                                                 7773  


----------------------- Page 18-----------------------

late  disclosures.    Nor  is  it  clear  that  less  severe  sanctions  such  as  excluding  the  



undisclosed  evidence  would  have  been  inadequate  to  cure  any  prejudice.    When  it  



decided to preclude Johnson's claims, the court was concerned there was not  enough  



time "a week before trial" to make up for the lack of disclosure to PAC.   But by the  



time the court issued its order  on March 11,  the  March  1  trial  date had already been  



rescheduled  to  June.    Sufficient  time  therefore  apparently  remained  to  cure  any  

prejudice.32  It was an abuse of discretion to preclude the claims without exploring lesser  



sanctions.  



        B.       PAC's Argument That The Subcontract Governs  



                 PAC appeals the superior court's finding that  Johnson's  extra work was  



not governed  by  the subcontract.    It argues that the court conflated waiver of select  



contractual provisions with total abandonment of the contract.  It contends that the terms  



of the agreement, the parties' conduct, and industry practice demonstrate that PAC and  



Johnson  intended  for  the  subcontract  to  govern  the  extra work  even  if  they  did  not  



"strictly follow" certain provisions in the subcontract.  Therefore, PAC argues, Johnson  



is  not  entitled  to  recover  damages  because  Johnson  did  not  satisfy  two  conditions  



precedent to payment:  the certified payroll and final payment application requirements.   



PAC  asserts  that  its  duty  to  pay  never  arose  because  Johnson  did  not  satisfy  these  



conditions, and Johnson is not entitled under the subcontract to payment for the extra  



work it performed.   



                 PAC's theory depends on its argument that the certified payroll and final  



payment  application  provisions  are  conditions  precedent.    Johnson  questions  that  



premise.   



                                                                                                               

        32       See Maines v. Kenworth Alaska, Inc., 155 P.3d 318, 325-26 (Alaska 2007)  

(holding two months before trial was sufficient to cure late discovery disclosure).  



                                                    -18-                                                 7773  


----------------------- Page 19-----------------------

                 A condition precedent is a prerequisite, an event, or an act that must occur  

or exist before a party's duty to perform under a contract begins.33  If the condition is  



not  fulfilled,  then  the  corresponding duty or duties do not  materialize,  and the party  

charged with satisfying the condition has no right to enforce the contract.34    



                 Because conditions precedent are viewed with disfavor, "a condition must  



be 'expressed in plain, unambiguous language or arise by clear implication' " to be  

enforceable.35  The purpose of this requirement, we have explained, is to reduce the risk  



of forfeiture and honor the parties' agreement.36  When we interpret a contract, our aim  



"is to give effect to the reasonable expectations of the parties."37  To do so, we consider  



the language of the disputed provision, the language of the contract as a whole, extrinsic  

evidence, and case law interpreting similar provisions.38  



                 PAC  posits  that  the  language  of  the  subcontract  establishes  that  the  



certified payroll and final payment application clauses  are conditions precedent.  The  



certified payroll clause provides that, if the Forest Service conditions PAC's payment  



on receipt of Johnson's certified payrolls, then Johnson "shall promptly furnish [PAC]  



with such required documentation."  It also says that PAC "may withhold payment until  



such  documentation  has  been  furnished."    The  final  payment  application  provision  



states  that  PAC's  final  payment  to  Johnson  "shall  in  no  event  become  due"  until  



Johnson submits, "as may be required by [PAC]:  (i) an affidavit that all payrolls, bills  



                                                                                                                

        33       Laybourn v. City of Wasilla , 362 P.3d 447, 453 (Alaska 2015).  



        34       See id. at 457.  



        35       Id. at 453 (quoting Jarvis v. Ensminger , 134 P.3d 353, 358 (Alaska 2006)).  



        36       Jarvis , 134 P.3d at 358; see also RESTATEMENT (SECOND) OF CONTRACTS  

§ 227 cmt. b (AM. L. INST .  1981).  

        37       Laybourn , 362 P.3d at 453 (quoting Peterson v. Wirum, 625 P.2d 866, 872  

n.10 (Alaska 1981)).  

        38       Id.  



                                                     -19-                                                 7773  


----------------------- Page 20-----------------------

for  materials  and  equipment,  and  all  other  indebtedness  of  [Johnson]  related  to  its  



performance of the Work, have been fully paid or otherwise satisfied, and (ii) complete  



and final lien waivers."   



                 We  are  not  convinced  that  these  provisions  are  conditions  precedent.   



While we recognize that a contract does not need any magic words to create a condition  

precedent,39 the subcontract here does not include any expressly conditional language.40   



PAC suggests that the clause stating that it "may withhold payment until" the certified  



payrolls have been provided establishes the condition precedent.  But that clause could  



also be read as  affecting the timing of payment or  authorizing a discretionary action  



rather than indicating a mandatory event that must occur before PAC's performance is  



due.   PAC's conduct supports this reading:   it paid all five of  the  invoices  Johnson  

submitted without certified payrolls.41   



                 Likewise, it is not clear whether the final payment clause empowered PAC  



to avoid paying Johnson altogether or merely to delay payment.  The clause authorized  



PAC  to withhold  payment  until Johnson submitted certain documents.    Some  courts  



have  interpreted  similar provisions  as  affecting  only  the timing  of payment, not the  

obligation itself.42  Another has interpreted a similar  clause as a promise to provide a  



                                                                                                              

        39       Jarvis , 134 P.3d at 359.   



        40       Cf., e.g., Laybourn , 362 P.3d at 454 ("subject to"); Klondike Indus.  Corp.  

v. Gibson, 741 P.2d 1161, 1165 (Alaska 1987) ("if").  

        41       See  Peterson,  625  P.2d  at  874  (holding  contractual  provision  was  not  

condition precedent because, inter alia, party 's  conduct showed  she  did not consider  

provision necessary for performance).   

        42       E.g., Koch v. Constr. Tech., Inc. , 924 S.W.2d 68, 73 (Tenn. 1996); Thos.  

J. Dyer Co. v. Bishop Int'l Eng'g Co. , 303 F.2d 655, 657, 659-61 (6th Cir. 1962); cf.  

Jarvis ,  134  P.3d  at  359  (considering  whether  provision  was  condition  precedent  or  

timing mechanism).   



                                                    -20-                                                7773  


----------------------- Page 21-----------------------

lien-release     affidavit    in   exchange      for   final   payment.43         Applied     here,    such  



interpretations  avoid  forfeiture  and  fulfill  the  primary  purpose  of  the  subcontract44 :   



PAC receives the bridge  free of obligation to Johnson  and Johnson receives payment  



for its work.   



                 When read as a whole, the contract further undermines PAC's argument.   



The  certified  payroll  and  final  payment  clauses  are  found  in  Article  Five  of  the  



subcontract.  The first paragraph of that Article provides that "all payments to [Johnson]  



are  dependent  upon,  as  a  condition  precedent,  and  not  due  until  [PAC]  receives  



payment from the [Forest Service] for [Johnson's] work, labor and material" (emphasis  



added).   It also states that Johnson must submit an invoice with receipts and original  



waivers of lien "[a]s a condition precedent to issuance of any payments by [PAC] to  



[Johnson]"   (emphasis   added).      These   clauses   show   that   PAC   knew   how   to  



unambiguously  create  a  condition  precedent  when  it  so  desired.    The  conspicuous  



absence  of  that  language  from  the  final  payment  application  and  certified  payroll  



provisions   casts  doubt  on  the  argument  that  they  were  intended  as   conditions  

precedent.45   For that  reason, and "the disfavor with which conditions precedent are  



viewed by the law,"46 we conclude that the provisions are not sufficiently unambiguous  



to be conditions precedent to Johnson's right to payment.  



                 Absent  a  condition  precedent,  a  nonbreaching  party  is  excused  from  

further performance only when there has been a material breach of the contract.47  A  



                                                                                                              

        43       See Solar Applications Eng'g, Inc. v. T.A. Operating Corp., 327 S.W.3d  

104, 109-10 (Tex. 2010).  

        44       Cf.  Prichard  v.  Clay,  780  P.2d 359,  362-63  (Alaska 1989)  (construing  

term as condition precedent because it was "principal if not sole object" of agreement).   

        45       Koch , 924 S.W.2d at 72-73.  



        46       Peterson, 625 P.2d at 874.  



        47       See RESTATEMENT (SECOND) OF CONTRACTS  § 237 cmt. a (AM. L. INST .  

1981).  



                                                    -21-                                                7773  


----------------------- Page 22-----------------------

material  breach  is  "one  that  will  or  may  result  in  the  other  party  not  receiving  

substantially what that party bargained for."48  A breach that is not material is a partial  



breach.  A partial breach may give rise to a cause of action, but does not excuse future  

performance.49   Though the nonbreaching party  may be  entitled to damages for the  



partial breach, it is still bound by the contract and may not abandon performance.50   



                 PAC does not argue that Johnson materially breached the contract.    Its  



argument that Johnson should be denied recovery under the subcontract rests entirely  



on  its  claim  that  the  certified  payroll  and  final  payment  application  provisions  are  



conditions precedent.  Because we  concluded that these provisions are not conditions  



precedent, Johnson's failure to comply with them is not a bar to recovery.  Therefore,  



even assuming the subcontract controlled, the superior court did not err by holding that  



Johnson was entitled to damages.  



        C.       Method Of Proving Damages  



                 There are four methods of proving damages in a construction lawsuit:  the  



actual  cost  method, jury  verdict  method,  total  cost  method,  and  modified  total  cost  

method.51  The preferred method is the actual cost method, which, as its name implies,  



identifies  the  actual  expense  incurred  from  the  alleged  breach  to  calculate  the  total  

claimed amount.52  If that method is not feasible, a contractor may use the jury verdict  



                                                                                                              

        48       State,  Dep't  of  Nat.  Res.  v.  Alaskan  Crude  Corp.,  441  P.3d  393,  401  

(Alaska 2018).  

        49      Alaska Energy Auth. v. Fairmont Ins. Co. , 845 P.2d 420, 423 n.3 (Alaska  

1993) ("For a partial breach the injured party can maintain action at once; but he is not  

permitted  to  stop  further  performance."  (quoting  ARTHUR  L.  CORBIN,  CONTRACTS,  

§ 946 at 811 (1951))).  

        50       23  WILLISTON  ON  CONTRACTS  §  63:3  (4th  ed.  2024);  RESTATEMENT  

(SECOND) OF CONTRACTS § 241 cmt. a (AM. L. INST .  1981).  

        51       Power Constructors, Inc. v. Taylor & Hintze , 960 P.2d 20, 41 (Alaska  

1998).  

        52       Id.   



                                                    -22-                                                7773  


----------------------- Page 23-----------------------

method to prove damages.53  The jury verdict method is a variation on the actual cost  



method.  Instead of showing the actual costs incurred, the plaintiff "present[s] evidence  



of the cost of additional work . . . [,] including any actual cost data, accounting records,  

estimates by law and expert witnesses, and calculations from similar projects."54    



                 The total cost and modified total cost methods are disfavored.55  The total  



cost  method  calculates  damages  by  subtracting  the  original  contract  price  from  the  

actual costs incurred (including a reasonable amount for profit).56  We have observed  



that this approach is "universally disfavored"57 because it makes so many assumptions:   



that the "plaintiff's costs were reasonable, that  [the] plaintiff was not responsible for  

any increases in costs, and that  [the] plaintiff's bid was accurately computed."58  Due  



to all of these assumptions,  a plaintiff contractor  must satisfy a four-part test  before  



being allowed to  rely on  the total cost method.  The plaintiff must  demonstrate  that:   



"(1) the nature of the particular losses make it impossible or highly impracticable to  



determine them with a reasonable degree of accuracy; (2) the plaintiff's bid or estimate  



was realistic; (3) its actual costs were reasonable; and (4) it was not responsible for the  

added expenses."59    



                                                                                                             

        53      N. Pac. Erectors, Inc. v. State, Dep't of Admin. , 337 P.3d 495, 507 (Alaska  

2013).  

        54       Power  Constructors ,  960  P.2d  at  41  (second  alteration  in  original)  

(quoting Mun. of Anchorage v. Frank Coluccio Constr. Co. , 826 P.2d 316, 325 (Alaska  

1992)).  A judge may use the jury verdict method in a bench trial, even though there is  

no jury.  See Delco Elecs. Corp. v. United States, 17 Cl. Ct. 302, 323 (Cl. Ct. 1989).  

        55       Power Constructors, 960 P.2d at 41.  



        56       Geolar, Inc. v.  Gilbert/Commonwealth Inc. of Michigan, 874 P.2d 937,  

944 (Alaska 1994).  

        57       Frank Coluccio Constr. Co. , 826 P.2d at 325.  



        58       Geolar, Inc., 874 P.2d  at  944 (cleaned up) (quoting Fairbanks N. Star  

Borough v. Kandik Constr., Inc. & Assocs., 795 P.2d 793, 798 (Alaska 1990)).  

        59      Id. at 945 (quoting Frank Coluccio Constr. Co. , 826 P.2d at 325).  



                                                   -23-                                                7773  


----------------------- Page 24-----------------------

                 PAC repeatedly urged the superior court to grant its motion for summary  



judgment  because  Johnson  did  not  meet  this  threshold  test.    The  court  agreed  that  



Johnson had not  satisfied the test but denied summary judgment because " [t]here are  



other  ways  to  prove  damages."    Before  the  trial  began,  the  court  granted  PAC  and  



Albin 's motion to prohibit Johnson from using the total cost method to prove damages.   



The court ultimately relied on the jury verdict method to calculate  some of Johnson's  



damages.   



                 On appeal, PAC repeats the  arguments  it made to the superior court.  It  



maintains that the court erred by denying summary judgment because Johnson made a  



total cost claim and failed to meet the requirements to rely on that method to calculate  



its damages.  It also claims that the subcontract required Johnson to prove damages with  



the actual  cost method and that Johnson cannot use the jury method because  its own  



failure to keep specific records is the reason it cannot show its actual costs.   



                 1.      Total cost claim  

                 We generally do not review a denial  of  summary judgment after trial.60   



But because this denial was based purely on a  legal issue rather than the presence of  

factual disputes that a trial could resolve, we will consider it on appeal.61   



                 PAC argues that the superior court erred by denying summary judgment  



because Johnson made a total cost claim and failed to meet the requirements to assert  



that method for calculating damages.  PAC's  argument assumes that Johnson made a  



total cost claim.  We disagree with PAC.   



                 Johnson's complaint alleged that PAC and Albin breached their contract  



for  extra  work,  which  they  agreed  to  compensate  on  a  time  and  materials  basis.   



Consequently,  Johnson's  claimed  damages  were  based  on  the  time  and  materials  it  



expended  performing  the  extra  work  -  its  actual  costs.    Though  Johnson's  initial  



                                                                                                             

         60      Baker v. Duffus, 542 P.3d 1153, 1156 (Alaska 2024).  



         61      Id.   



                                                   -24-                                                7773  


----------------------- Page 25-----------------------

demand  resembled  a  total  cost  claim  because  it  estimated  the  amount  owed  by  



subtracting the amount it was paid under Work Order Nos. 1 and 2 from its overall  



expenditures, it was not a total cost claim.  The central feature of a total cost claim "is  



a  comparison  between  the  contractor's  initial  estimates  and  the  actual  cost  of  

performing the contract."62   Here, there were no initial estimates for the extra work  



because the parties agreed to payment on a time and materials basis.  The superior court  



ably distinguished the  costs that PAC agreed to reimburse from those it did not, thus  

avoiding the causation concerns that attend the total cost method.63   It did not err by  



denying summary judgment.  



                 2.      Jury verdict method  



                 PAC next argues that the court erred by using the jury verdict method to  



determine Johnson's damages.  PAC contends that the subcontract requires the actual  



cost method to calculate damages.  It argues that two provisions in the subcontract - a  



recordkeeping clause and a changes clause - show that the parties agreed to measure  



damages under the actual cost method.  The recordkeeping clause required Johnson to  



keep "full and detailed accounts, books and records as are necessary ."   The changes  



provision stated that Johnson "shall keep and present, in any form as [PAC] may direct,  



a correct amount of the net cost of any extra labor and materials" for changes in the  



work.  Because the subcontract required actual costs, PAC continues, Johnson's failure  



to present an actual cost claim bars it from recovering any damages.   



                 PAC  relies  on  our  decision  in  North  Pacific  Erectors,  Inc.  v.  State,  

Department  of  Administration  for  support.64    In  that  case  we  considered  whether  a  



contractor could recover damages under the jury verdict method for a  differing  site  



                                                                                                             

        62      Power Constructors, Inc. v. Taylor & Hintze, 960 P.2d 20, 41 (Alaska  

1998) (quoting Geolar, Inc., 874 P.2d at 944).  

        63      Id. at 41-42, 44.   



        64       337 P.3d 495 (Alaska 2013).   



                                                   -25-                                                7773  


----------------------- Page 26-----------------------

conditions claim.65  We held that the contractor could not recover under the jury verdict  



method because the contract required a different method for calculating damages.66  The  



contractor, we said, was "bound by the express provisions of the contract" requiring  

proof of actual damages.67   



                 The  contract  at  issue  in  North  Pacific  differed  significantly  from  the  



subcontract  here.    That  contract  expressly  provided  that  the  "contractor  must  prove  



actual damages" for any claims for additional compensation and that the "[t]otal cost,  



modified  total  cost  or  jury  verdict  forms  of  presentation  of  damage  claims  are  not  

permissible  to  show  damages."68    In  the  event  of  a  differing  site  condition,  the  



contractor was required "to keep an accurate and detailed record" of the "actual 'cost  

of the work' done under the allegedly differing site condition."69  The contract further  



provided that "[f]ailure to keep such a record shall be a bar to any recovery by reason  

of such alleged differing site conditions."70   In contrast, the  subcontract  here  did not  



identify a particular measure for damages.  And unlike North Pacific , recovery is not  



conditioned  on  compliance  with  the  recordkeeping  requirements.    The  subcontract  



between PAC and Johnson is silent about the method of proving damages.  Therefore,  



even assuming the subcontract governed, we are not persuaded that the parties agreed  



that damages must be proven by the actual cost method.    



                 PAC also argues that case law prohibits the use of the jury verdict method  



in this case.    North Pacific , it says, held that a plaintiff cannot use the jury verdict  



method  when  contractual  recordkeeping  provisions  were  at  issue.    Furthermore,  it  



                                                                                                                   

         65      Id. at 506-09.  



         66      Id.   



         67      Id. at 507.  



         68      Id. at 506.  



         69      Id.  



         70      Id. (alteration in original).  



                                                      -26-                                                   7773  


----------------------- Page 27-----------------------

asserts, a plaintiff "is not excused" from using the actual cost method "by its failure to  



keep records of actual costs."   And because Johnson could have used the actual cost  



method  if  it  had  retained  its  records,  PAC  reasons  that  it  was  error  to  calculate  its  



damages under the jury verdict method.   



                 PAC's reading overstates our holding in North Pacific .  Our decision in  



that case rested on the express contractual provisions that (1) required damages claims  



to be proven by actual costs and (2) prohibited recovery when the contractor failed to  

keep records of the actual cost of work done under allegedly different conditions.71  We  



held  that  the  contractor  was  barred  from  recovery  "because  it  did  not  substantially  

comply"  with  those  express  damages  and  records  provisions.72    Contrary  to  PAC's  



argument, we did not hold that a contractor cannot use the jury verdict method when  



"specific contractual record-keeping requirements were not at issue."   



                 Nor did we say that a plaintiff cannot use the jury verdict method unless  



it has shown that a more reliable method is unavailable for reasons beyond its control.   



The only limitation that we have placed on the jury verdict method is that it cannot be  

used  when  a  more  reliable  method  of  computing  damages  is  available.73    This  



requirement reflects our general preference for the actual cost method while recognizing  

that "a contractor need not prove damages with mathematical precision."74  Although  



North Pacific  discussed a federal claims court decision that rejected the jury verdict  



method because the plaintiff failed to show "a justifiable inability to substantiate the  



                                                                                                              

        71       Id. at 506-07.  



        72       Id. at 509.  



        73       Id. at 507.  



        74       K & K Recycling, Inc. v. Alaska Gold Co., 80 P.3d 702, 722 (Alaska 2003)  

(quoting Mun. of Anchorage v. Frank Coluccio Constr. Co. , 826 P.2d 316, 325 n.12  

(Alaska 1992)).  



                                                    -27-                                                7773  


----------------------- Page 28-----------------------

amount  of  his  resultant  injury  by  direct  and  specific  proof,"  we  did  not  adopt  its  

holding.75    



                 PAC's  position  runs  counter  to  our  two-tiered  standard  for  proving  



uncertain  damages.    A  contractor  must  prove  the  fact  of  damages  by  reasonable  



certainty - that is to say, that it suffered a loss as a result of the breach of contract -  

but the amount of damages requires a lesser quantum of proof.76  It need only present  



"  'some  data'  to  enable  a  trier  of  fact  to  'reasonably  estimate'  the  amount  of  those  

damages."77    Direct  evidence  of  specific  costs  is  typically  the  most  probative  and  



persuasive.  But indirect evidence, such as expert witness estimates and costs of similar  



projects,  can  also  provide  a  reasonable  basis  for  calculating  damages.    Where  the  



contractor has already clearly proven injury, restricting indirect evidence because the  



contractor failed to demonstrate that it was unable to keep better records unduly burdens  

recovery.78   We therefore hold that "a contractor's failure to demonstrate that it was  



                                                                                                                

         75      N. Pac. Erectors , 337 P.3d at 508 (quoting Joseph Packard's Sons Co. v.  

United States, 532 F.2d 739, 742 (Ct. Cl. 1976)).    

         76      Downing v. Shoreside Petrol., Inc. , 528 P.3d 874, 887 (Alaska 2023); see  

also K & K Recycling, Inc., 80 P.3d at 722 (applying standard to contractors).  

         77      Downing , 528 P.3d  at 886 (quoting Sherbahn v. Kerkove, 987 P.2d 195,  

200 (Alaska  1999)).  

         78      We do not share the concern that courts using the jury verdict method will  

adopt and extend "unrealistic assumptions . . . , greatly multiplying an award beyond  

reason."  Dawco Constr., Inc. v. United States , 930 F.2d 872, 882 (Fed. Cir. 1991).  The  

court here primarily relied on the actual cost method.   It seems to have used the jury  

verdict method only to determine damages for the boat and snowmachine use, Morris  

Johnson's  labor,  and  Johnson's  equipment.    For  each  of  these  awards,  it  carefully  

considered the evidence presented.  It rejected Johnson's estimates as uncorroborated  

and  fashioned  an  award  based  on  reason  and  reliable  evidence.    The  modest  sum  

awarded  was  substantially  less  than  Johnson's  claims,  demonstrating  the  court's  

"ability to sift through the chaff and find the grain."  Power Constructors, Inc. v. Taylor  

& Hintze, 960 P.2d 20, 44 (Alaska 1998).  Even under the jury verdict method, the  

plaintiff  must  present  sufficient  evidence  for  a  court   to   fairly  and  reasonably  

  



                                                     -28-                                                 7773  


----------------------- Page 29-----------------------

unable  to  keep  better  records  does  not  necessarily  preclude  use  of  the  jury  verdict  

method."79    



        D.      Damages Award  



                Both Johnson  and  PAC  challenge  the  superior  court's damages  award.   

The determination of damages is a finding of fact that we review for clear error.80  We  



will  affirm the finding unless, "after a thorough review of the record, we come to a  

definite and firm conviction that a mistake has been made."81   



                1.      Morris Johnson's labor  



                The  superior  court  prevented  Johnson  from  recovering  damages  for  



Morris Johnson's labor because it failed to provide sufficient documentation of  those  



damages during discovery.  But the court made a contingent finding that, if allowed to  



pursue the claim at trial, Johnson would have been awarded $128,700 in damages for  



Morris Johnson's labor.  PAC argues that the court erred because Johnson offered no  



evidence supporting his claimed hourly rate or  hours worked.    PAC also takes issue  



with the court's "speculat[ion] about the number of hours" he worked and use of a  



multiplier with "no basis in evidence."   



                The record contains sufficient evidence to provide a reasonable basis for  



computing  the  cost  of  Morris  Johnson's  labor.    Morris  Johnson  estimated  that  he  



worked 1,427 hours on the extra work.  The only corroborating evidence presented at  



trial  was  the  set  of  certified  payrolls  from  the  2011-12  winter.    Based  on  those  



                                                                                                           



approximate damages.  District of Columbia v. Org. for Env 't  Growth, Inc., 700 A.2d  

185, 204 (D.C. 1997); New Pueblo Constructors, Inc. v. State, 696 P.2d 185, 196 (Ariz.  

1985) (en banc);  WRB Corp. v. United States, 183 Ct. Cl. 409, 425 (Ct. Cl. 1968).  

        79      Rustler Constr., Inc. v. District  of Columbia, 211 A.3d 187, 198 (D.C.  

2019).    

        80      Galipeau v. Bixby, 476 P.3d 1129, 1134 (Alaska 2020).  



        81      Burton  v.  Fountainhead  Dev.,  Inc. ,  393  P.3d  387,  392  (Alaska  2017)  

(quoting Laybourn v.  City of Wasilla, 362 P.3d 447, 453 (Alaska 2015)).  



                                                  -29-                                               7773  


----------------------- Page 30-----------------------

documents, the court estimated that Morris Johnson worked  10 hours a day for 20 days  



constructing the ice bridge in February and March 2012.  It stated it had "no doubt" that  



he  worked more than that during the entire project but because he did not keep time  



records, it would "assume that [over the life of the project] he worked three times th[e]  



hours" indicated in the payroll.  The court calculated Morris Johnson's hourly rate based  



on the difference between  "wet" (a  crane rental with an operator)  and "dry"  (a crane  



without an operator) rental rates.  Morris Johnson testified that his crane's wet rate was  



$385 and the dry rate was $225, giving the court a reasonable basis to estimate that the  

value of an experienced crane operator's time is $130 per hour.82    



                 And it was not clear error to triple  the number of hours Morris Johnson  



worked.  The court's estimate was based on the hours Morris Johnson worked for two  



months in 2012.  But Morris Johnson performed extra work for PAC for  at least two  



years.  It was reasonable for the court to estimate that he provided triple that amount of  



labor over the course of two years.   



                 It was, however, a clear error to conclude that Morris Johnson worked the  



equivalent of 330 hours in the 2011-12 winter.  The court estimated that Morris Johnson  



worked 10 hours a day for 20 days in the winter of 2011-12.    Because  two of those  



hours were at an overtime rate, it concluded that he effectively worked 11 hours per day  



for 20 days.  Multiplying those hours by the number of days amounts to 220 hours at  



the worksite that winter, not 330.  We therefore reverse the award for Morris Johnson's  



labor and remand for the court to recalculate these damages.  



                 2.      Snowmachines  



                 Like Morris Johnson's labor, the superior court precluded Johnson from  



pursuing its claim for damages for the snowmachine use.   But it allowed Johnson to  



                                                                                                             

        82       The  court based  its finding on  the difference  between  the wet  and  dry  

rates, which would be $160.  In closing, Johnson agreed that $130 per hour - the hourly  

rate for crane operators - was reasonable for his labor.   



                                                   -30-                                                7773  


----------------------- Page 31-----------------------

present evidence for that claim and made contingent findings on it.  The court concluded  



that PAC would owe Johnson $15,000 for the snowmachines if its order precluding the  



claim was reversed on appeal.   



                 PAC  argues  that  the  court's  finding  is  clearly  erroneous  because  no  



evidence  at  trial  supported  Johnson's  calculation  of  the  number  of  days  it  used  the  



snowmachines.    It  objects  to  the  court's  making  its  contingent  findings  based  on  



Johnson's certified payrolls, which it argues the court itself found to be inaccurate.  But  



the  superior  court  only  said  that  the  documents  were  not  "entirely  accurate."    The  



inaccuracies were in the hours, payment amounts, and check numbers, not the number  



of days or employees who worked in the 2011-12 winter.  In contrast, the court found  



that the number of days indicated in the payrolls (3 employees and 20 days) was more  



credible than Johnson's 2016 estimates (17 days) or Morris Johnson's testimony (36  



days).   Those documents were enough for the court to reasonably estimate Johnson's  

damages.83  



                 3.      Cranes  



                 The court  ordered  PAC to pay Johnson $99,000 for overwintering two  



cranes at the worksite.    The court found that PAC agreed to reimburse Johnson for  



overwintering the cranes but "never agreed upon a mechanism for that reimbursement."   



Finding Johnson's proposed monthly rental rates "too speculative," the court used the  



crane mobilization rates as a "reasonable, albeit rough" means of estimating the value  



of leaving the cranes  on  site  for two winters.   The parties agreed that mobilizing  or  



demobilizing a crane cost $16,500.  The court therefore reasoned that remobilizing the  



crane left in the 2011-12 winter would have cost $33,000.  Similarly, demobilizing and  



remobilizing the two cranes left in the 2012-13 winter would have cost $66,000.    



                                                                                                             

        83       Cf.  Griffith v. Hemphill, 521 P.3d 584, 590-91 (Alaska 2022) (holding  

testimony of single witness sufficient to provide reasonable basis to calculate damages).  



                                                   -31-                                                7773  


----------------------- Page 32-----------------------

                 Both parties take issue with the court's methodology.  Johnson contends  



that it has no "logical nexus" to the length of time the cranes were at the worksite and  



asks for reimbursement based on a monthly rental rate; PAC says the court's approach  



has "no basis in the testimony" and argues that Johnson should have been awarded  



nothing without presenting reliable evidence of crane rental rates.    



                 The court did not err by rejecting Johnson's proposed rental rates.  At trial,  



Morris  Johnson  agreed  that  charges  for  equipment  time  under  a  time  and  materials  



agreement can vary.   He testified the charge  could be based on a wet rate, dry rate,  



monthly rate, or hourly rate.  He also agreed that Johnson and PAC never finalized the  



terms of the agreement for the extra work, including the crane rates.  The superior court  



therefore found the parties did not agree on a mechanism to reimburse Johnson for the  



overwintered  cranes.    It did  not err by disregarding Johnson's proposed rental rates  

because Johnson did not establish that PAC agreed to reimbursement on that basis.84   



                 But other evidence provided the court with a reasonable basis to compute  



damages for the cranes based upon the cost of mobilization.  The court determined that  



PAC was responsible for the delays causing Johnson to leave the cranes at the worksite.   



Neither party disputes this finding.    Testimony supports the court's finding that PAC  



avoided the costs of demobilizing  and remobilizing the cranes by  requiring them to  



remain at the worksite both winters.  And the parties agreed that the value of each crane  



mobilization or demobilization was $16,500.  The superior court thus had a reasonable  



basis to estimate that PAC owed Johnson $99,000 for the overwintered cranes.   



                 4.      Other equipment  



                 The superior court denied recovery for Johnson's other equipment claims,  



finding   its   proposed   rental   rates   "too   variable"   and   "untethered   to   objective  



                                                                                                             

        84       See  City of Whittier v.  Whittier Fuel & Marine Corp., 577 P.2d 216, 224  

(Alaska 1978) (holding evidence did not support damages award because plaintiff failed  

to prove damages were caused by defendant's wrongful conduct).  



                                                   -32-                                                7773  


----------------------- Page 33-----------------------

contemporaneous proof of a times  [sic] and materials agreement."  Johnson argues the  



court erred because the evidence presented at trial - Morris Johnson's testimony and  



expert testimony regarding equipment rental rates - provided a reasonable basis for  



computing the award.   



                 Johnson correctly asserts that the party seeking damages must provide a  

reasonable basis for computing the award.85  But the evidentiary standard for awarding  



difficult-to-ascertain  damages is two-tiered.86    As previously discussed, the plaintiff  



must provide a reasonable basis for computing the amount of an award.87  But Johnson  



must prove the fact  of damages with reasonable certainty.88   



                 Here,  the  superior  court  found  that  Johnson  failed  to  prove  the fact  of  



damages  for  the  other  equipment.    The  court  found  that  there was  no  agreement  to  



reimburse      Johnson      for   each    piece    of    equipment      for    which     Johnson      sought  



reimbursement.    The evidence supports this finding.  PAC's proposed change order  



contemplated payment for an excavator, a loader, and a bulldozer.  There is no evidence  



of  an  agreement  that  PAC  would  pay  Johnson  for  any  other  equipment  it  used  to  



perform the extra work.  And although Morris Johnson testified that he provided  the  



first project supervisor with his rental rates, the second project  supervisor testified he  



never received any rates when he tried to negotiate a change order with Morris Johnson .   



Morris Johnson also acknowledged that they never finalized a rental agreement and that  



equipment rates under a time and materials arrangement could vary.  Further, Johnson's  



dramatically changing  estimates  for  the equipment costs  -  ballooning from  around  



$500,000  for 23 pieces of equipment  before litigation  to  $2.4  million  for around 30  



pieces  in pretrial discovery  and nearly  $3  million  for over 40 pieces  at trial, before  



                                                                                                                

         85      Downing v. Shoreside Petrol, Inc., 528 P.3d 874, 887 (Alaska 2023).  



         86      Id.  



         87      Id.   



         88      See id.  



                                                     -33-                                                 7773  


----------------------- Page 34-----------------------

falling  to  about  $2.5  million  at  closing  -  indicates  that  these  damages  are  merely  



speculative.    



                 5.      Boat use  



                 The superior court initially found that PAC owed Johnson $30,000 for its  



boat use:  $25,000 for the cost of the boat and $5,000 for wear and tear.    On PAC's  



motion to reconsider, the court reduced the award to $10,000.   It  reasoned  that PAC  



was not responsible for reimbursing Johnson for the purchase price of the boat and wear  



and tear, but PAC  still owed Johnson transportation costs.  The court  estimated those  



costs based on the  current value of the boat after PAC's use, which  it assumed to be  



$15,000  "admittedly  without  any  real  evidence  of  the  amount  of  the  reduction."   



Because Johnson purchased the boat for $25,000, the court ordered PAC to pay Johnson  



the $10,000 for the use of the boat.   



                 Both parties appeal this award.  PAC challenges it as speculative and says  



that the court should not have awarded any damages for the boat.  Johnson says that the  



court should have awarded it $61,000 and argues that testimony at trial established that  



PAC agreed to rent the boat for $1,000 per day and used it over 40 times.   

                 Damages must be supported by evidence.89  The superior court candidly  



admitted it had no evidence to support the amount of damages it awarded.  We therefore  



vacate the damages award for the boat use and remand for recalculation.  



         E.      Prevailing Party Determination And Attorney's Fees   



                 The superior court determined that PAC was the prevailing party under  



Rule 68(b), finding that Johnson's total award  was less than 90% of PAC's offer of  



judgment.  PAC and Albin's $243,000 offer of judgment was "inclusive of prejudgment  



interest."  The court calculated Johnson's prejudgment interest beginning June 7, 2017.   



It  concluded  interest  began  accruing  on  that  date  because  that  was  the  date  when  



Johnson made its first demand for a specific amount of payment.   



                                                                                                             

         89      See Dihn v. Raines , 544 P.3d 1156, 1177 (Alaska 2024).   



                                                   -34-                                                7773  


----------------------- Page 35-----------------------

                 Johnson  argues that  the  court erred when it chose that  date.90    Johnson  



argues that prejudgment interest should have run from the day the parties entered into  



the subcontract:  August 23, 2011.  In the alternative, Johnson says that it  should run  



from at least August 8, 2013 -  the last day Johnson recorded hours working on the  



project.  Johnson asserts that this is the date that PAC "unquestionably knew" that the  



extra work was completed and that they owed Johnson compensation.   



                 We  see no error in the court's decision.   Ordinarily in contract disputes,  

"prejudgment interest runs from the date the claim accrues."91  In Hofmann v. von Wirth,  



we held that interest accrues when a party knows or should know the  value of  a  debt  

owed to another.92  In that case we reviewed a superior court's order requiring an ex- 



husband to reimburse his ex-wife for half of the expenses she incurred maintaining  

property they formerly shared.93  The order included prejudgment interest from the date  



the  ex-wife  began  paying  the  costs  of  upkeep,  even  though  she  did  not  demand  

reimbursement until years later.94  We reversed, holding that "a demand was necessary  



for interest to begin to accrue."95  We were guided by the principle that "a party  [that]  



cannot  ascertain  the  amount  of  [its]  obligation  should  not  be  charged  interest  for  a  



                                                                                                                

         90      Johnson also says that the superior court erred in finding that PAC 's Rule  

68 offer was not an invalid joint offer.  It offers no legal theory or support for its claim,  

instead  merely  making  a  "cursory  statement  in  the  argument  portion  of  the  brief."   

Casciola v. F.S. Air Serv., Inc., 120 P.3d 1059, 1062 (Alaska 2005).   Points that are  

inadequately briefed are considered waived.  Id.  

         91      K & K Recycling, Inc. v. Alaska Gold Co. , 80 P.3d 702, 724 (Alaska 2003).  



         92      907 P.2d 454, 455-57 (Alaska 1995).  



         93      Id. at 454-55.  



         94      Id.   



         95      Id. at 457.  



                                                     -35-                                                 7773  


----------------------- Page 36-----------------------

failure to meet this obligation."96  The ex-husband could not have been said to have a  



duty to reimburse his ex-wife when he had no knowledge of the sums she expended.   



                Johnson had to make a demand for payment to alert PAC of its obligation  



to pay.  The parties agreed that Johnson would be compensated on a time and materials  



basis  for  the  extra  work.    Even  though  PAC  assumed  that  it  owed  Johnson  some  



outstanding payment, PAC had no way of knowing the precise  amount until Johnson  



sought payment.  But Johnson did not submit an invoice.  The first time that Johnson  



gave PAC an account of the time and materials expended on the extra work was June  



7, 2017.   The superior court therefore did not err by  calculating prejudgment interest  



from June 7, 2017, as that was the date that PAC "ascertain[ed] the amount of  [its]  

obligation."97  



                Johnson argues that no demand  is necessary when a debtor  is generally  



aware of its debt, reading Hofmann  as "expressly predicated on the obligator's lack of  



knowledge concerning the obligation owed."  On the contrary, Hofmann makes it clear  



that the only time a demand is not needed is when the sum owed is liquidated or easily  

ascertainable.98    We  observed  that  no  other  court  had  issued  a  decision  "where  



[prejudgment interest] was awarded against a party who had no knowledge of the sums  



for which she might be liable.  When [prejudgment interest] is awarded, it is on amounts  

that are either liquidated or ascertainable."99   



                PAC  could  not  have  been  able  to  ascertain  the  amount  of  its  debt  to  



Johnson on August 23, 2011 because the parties had not yet agreed to the extra work  



by that date.  PAC could not have owed Johnson payment for work that had not even  



been contemplated yet.  And even though it knew that Johnson had completed the extra  



        96      Id. at 456.  



        97      Id.  



        98      Id. at 456-57.  



        99      Id. at 456 (footnotes omitted).  



                                                 -36-                                             7773  


----------------------- Page 37-----------------------

work by August 8, 2013, PAC had no way of knowing the amount it owed Johnson for  



the work compensated on a time and materials basis.  Even Johnson's estimates of the  



amount due changed dramatically over the course of litigation.  The superior court did  



not err by choosing  June 7, 2017  as the date on which prejudgment interest began to  



accrue.   



       CONCLUSION  



               We   REVERSE   the   preclusion   of      Johnson's   damages   claims     for  



snowmachine  use  and  Morris  Johnson's  labor.    We  VACATE  the  prevailing  party  



determination   and   resulting   attorney's   fee   award.      We   REMAND   for   further  



proceedings, including reconsideration of damages for Morris Johnson's labor and the  



boat  use,  consistent with  this opinion.  We  otherwise AFFIRM  the  superior  court's  



judgment.    



                                             -37-                                        7773  

Case Law
Statutes, Regs & Rules
Constitutions
Miscellaneous


IT Advice, Support, Data Recovery & Computer Forensics.
(907) 338-8188

Please help us support these and other worthy organizations:
Law Project for Psychiatraic Rights
Soteria-alaska
Choices
AWAIC