Title 18 . Environmental Conservation
Chapter 72 . Administrative Enforcement
Section 600. Application for department approval

18 AAC 72.600. Application for department approval

(a) A person who constructs, alters, installs, modifies, or operates any part of a nondomestic wastewater treatment works or disposal system must first have written department approval of engineering plans submitted under this section.

(b) If construction, alteration, installation, modification, or operation has not begun within two years after issuance of plan approval, the approval is void, and plans must be resubmitted to the department for review and approval.

(c) Engineering plans required by (a) of this section must include

(1) the location of proposed or existing improvements, wastewater treatment works and disposal systems, sewers, drinking water supply lines, drinking water sources, and waters in the vicinity of the proposed system;

(2) detailed flow diagrams showing the physical and chemical composition and amount of each nondomestic wastewater disposal;

(3) a statement identifying persons who will own, operate, and maintain the proposed system;

(4) a description and timetable of the proposed construction or other activity;

(5) information on sludge handling and disposal from the proposed treatment works; and

(6) other information the department requires to assess compliance with this chapter.

(d) As the department deterimines necessary to ensure compliance with this chapter and adequately protect public health, public and private water systems, and the environment, the department will attach terms and conditions, including monitoring, sampling, and reporting conditions, to submitted plans.

(e) An accurate and complete set of as-built drawings for nondomestic wastewater treatment works and disposal systems with a discharge greater than 10,000 gallons per day must be submitted to the department within 90 days after the project's startup date. The department will, in its discretion, waive this requirement if, after an onsite inspection, it finds that the system was built as approved.

History: Eff. 6/30/90, Register 114; am 1/17/2002, Register 161

Authority: AS 44.46.020

AS 46.03.010

AS 46.03.020

AS 46.03.050

AS 46.03.090

AS 46.03.710

AS 46.03.720


Note to HTML Version:

The Alaska Administrative Code was automatically converted to HTML from a plain text format. Every effort has been made to ensure its accuracy, but neither Touch N' Go Systems nor the Law Offices of James B. Gottstein can be held responsible for any possible errors. This version of the Alaska Administrative Code is current through June, 2006.

If it is critical that the precise terms of the Alaska Administrative Code be known, it is recommended that more formal sources be consulted. Recent editions of the Alaska Administrative Journal may be obtained from the Alaska Lieutenant Governor's Office on the world wide web. If any errors are found, please e-mail Touch N' Go systems at E-mail. We hope you find this information useful. Copyright 2006. Touch N' Go Systems, Inc. All Rights Reserved.

Last modified 7/05/2006